Every job ends the same way: the big work is done, and a dozen small things are not. A cabinet door rubs, an outlet cover is missing, there's a scuff on the hallway wall, the bathroom fan rattles. A punch list puts all of those items on one page, with who fixes each one and by when, so the job actually closes and the final payment comes in.

This free punch list template is built for residential and light commercial jobs: remodels, new construction, tenant fit-outs and service work with several trades. Download it as an editable Word document, an Excel workbook (one row per item, ready to sort and filter) or a printable PDF with the buttons above.

What's in the punch list template

The template prints on Letter paper:

  • Your business details and license number
  • Project number, walkthrough date, who walked the job, and the target completion date
  • Customer or owner and project details: job site address, contract date, project manager
  • A priority and status key so everyone reads the list the same way
  • The punch list table: item number, location or room, description, trade or person assigned, priority, due date and status, with numbered lines on the first page and a continuation page for long lists
  • Sign-off: a short statement that the listed items are complete, with signature lines for the customer and your company

Replace everything in [square brackets] with your own details. In the Excel version, every item is a row, so you can sort by trade, by room or by due date.

How to run a punch list walkthrough

1. Walk it yourself first. Before the customer sees the finished job, walk every room with the template and fix what you find. A customer who finds forty items stops trusting the work; a customer who finds four signs off.

2. Schedule the walkthrough when the job is substantially complete. Fixtures in, power and water on, systems running, debris out. If whole sections are unfinished, you'll get a to-do list, not a punch list.

3. Walk in a fixed order. Room by room, clockwise, top to bottom: ceiling, walls, trim, doors and windows, floor, then fixtures and equipment. Test things: open every door and window, run every faucet, flip every switch, run the HVAC, flush the toilets.

4. Write each item so someone else can fix it. "Kitchen: cabinet door left of the sink rubs the face frame, adjust hinge" can go straight to a carpenter. "Fix cabinets" can't. Add a photo number if you take pictures.

5. Assign every item. One trade or one person per line. If an item needs two trades (patch the drywall, then paint), write it as two items, in order.

6. Set a priority and a due date. The key on the template uses three levels:

  • A: safety, code or anything that stops the customer from using the space (a dead circuit, a leak, a missing handrail)
  • B: must be fixed before final payment (a door that won't latch, a cracked tile)
  • C: cosmetic (touch-up paint, caulk lines, a scuffed baseboard)

7. Agree on the list before you leave. Both of you initial the list, or at least agree it's complete. New items found later go on as new numbered lines, with the date they were added. This stops the list from growing forever.

8. Close each item and get the sign-off. Mark items done with the date, walk the finished items with the customer, and have them sign the completion statement at the bottom.

Sample punch list: a filled-in example

Here's how part of a punch list might look at the end of a kitchen and bathroom remodel. The items are illustrations, not a checklist for your job.

# Location Description Assigned to Priority Due Status
1 Kitchen Under-cabinet light over the sink doesn't turn on; check connection Electrician A 3/12 Done 3/11
2 Kitchen Cabinet door left of the sink rubs the face frame; adjust hinge Carpenter B 3/12 Done 3/11
3 Kitchen Caulk gap where the backsplash meets the countertop, right end Tile setter C 3/14 Open
4 Hall bath Shower valve trim plate loose; secure and seal Plumber B 3/13 In progress
5 Hall bath Exhaust fan rattles on start-up; check damper and mounting Electrician B 3/13 Open
6 Hallway Scuff and ding on the wall outside the bath door; patch and touch up Painter C 3/14 Open
7 Whole house Remove protection film from new window frames; final clean Cleaning crew C 3/15 Open

Notice that every line names a place, says exactly what's wrong and has one owner. That's what makes the list work when it's sent to five different people.

Punch list items that come up on most jobs

Use these to prepare for your own walkthrough. Which ones apply depends on the job.

  • Doors and windows: doors that stick, swing open on their own or don't latch; missing door stops; windows that don't lock; screens missing; torn weatherstripping.
  • Drywall and paint: nail pops, visible seams, dings, missed spots, paint on hinges, outlets or glass, uneven caulk lines.
  • Trim and cabinets: open miters, gaps at the wall, doors and drawers out of alignment, missing pulls or bumpers.
  • Electrical: missing or crooked cover plates, switches that don't control the right light, dead outlets, GFCI outlets that don't trip or reset, fixtures not working.
  • Plumbing: drips under sinks, slow drains, loose toilets or fixtures, no hot water at a fixture, missing escutcheons.
  • HVAC: registers missing or rattling, rooms that don't heat or cool, thermostat not set up, filters not replaced after construction dust.
  • Flooring and tile: cracked or hollow-sounding tiles, missing grout, gaps at transitions, scratches in finished floors.
  • Exterior: downspouts not connected, gaps in caulk around penetrations, damaged landscaping, debris left on site.
  • Paperwork: manuals and warranty cards, paint color and product list, keys and remotes, final inspection sign-off.

Punch lists with subcontractors

When subs do part of the job, the punch list becomes their to-do list. Sort it by trade (easiest in the Excel version), send each sub only their lines, and give each a due date that leaves you time to check the work before the customer's final walkthrough.

Put the punch list in your subcontract too. Our subcontractor agreement template lets you hold retainage until final completion and acceptance of the work; a sub's punch list items are the clearest measure of "complete." If a punch list item turns into extra work (the customer asks for something new during the walkthrough), it isn't a punch list item: write it up on a change order and price it.

Punch list, change order, work order: which document when

  • Punch list: the end-of-job list of small fixes to finish work that's already in the contract. No extra charge.
  • Change order: a signed change to the scope or price. New work, new money.
  • Work order: the job ticket for a single visit or task, such as a return visit to fix one item.
  • Invoice: the final bill, usually sent once the punch list is signed off.

Final payment and the punch list

Most disputes at the end of a job are about whether it's finished. The punch list answers that question in writing. Three habits help:

  • Define completion in the contract. For example, final payment is due when the work is complete and the punch list items are done, or within a set number of days of substantial completion.
  • Don't let small items hold up a big payment. Some contractors agree to hold back a fixed amount for open punch items instead of the whole final payment, released when the list is signed off.
  • Date everything. The walkthrough date, the date each item was added and the date each was finished. If the customer keeps adding items weeks later, the dates show it.

Payment terms on home improvement jobs are also shaped by state law. Check with your licensing board or an attorney before you write holdback terms into a contract.

When to move to software

A paper punch list works fine for one job at a time. When you're closing several jobs a month with subs on each, the problems show up: photos live on someone's phone, subs don't see their items until someone emails them, and nobody knows which list is current. Field service and project tools let you add items with photos on site, assign them to a person, and close them from a phone. Compare options in our guides to contractor scheduling software and field service management apps.